CURRENT FULFILMENT TIMES
Current Estimated Order timeframes
CABLE - 16 weeks ex works
TRANSFORMER - 20 weeks ex works
SWITCHGEAR - 16 weeks ex works
SUBSTATIONS - 16 weeks ex works
Current Estimated Shipping timeframes
CABLE - 4-6 weeks
TRANSFORMER - 3-4 weeks
SWITCHGEAR - 3-4 weeks
SUBSTATIONS - 4-6 weeks airfreight

Need it Faster?
WHEN YOU NEED IT FASTER...
We know time is money, and sometimes you just don't have the time to wait.
Check out our current Stock listings, we could have just what you need, ready to go.
Or use our Critical Sourcing services for urgent requirements - we can find what you're looking for.